Valleycrest Timeline 1994-2005
1994: Valleycrest listed on NPL
1995: OEPA approves Remedial Investigation/Facility Study (RI/FS) Phase 1 Work Plan (OEPA)
1998: EPA Administrative Order of Consent (AOC), Landfill Gas Abatement System installed, Area 5 drum removal initiated
2000: Preliminary Investigation (PI) initiated (OEPA)
2001: Area 5 drum removal completed (USEPA)
2002: Area 1 drum removal & tanker investigation completed. Area 5 Vapor Extraction (VE) initiated. (USEPA)
2002: PI completed. OEPA Approved Revised RI/FS schedule (OEPA)
2003: Area 5 VE to be completed. Area 1 VE to be initiated. (USEPA)
2003: Remedial Investigation (RI) ongoing (OEPA)
2004: Area 1 VE to be completed (USEPA)
2004: RI Report due to OEPA (OEPA)
2005: Feasibility Study (FS) Report due to OEPA (OEPA)